Eurodatum / Grid access tracker
Grid access tracker · v1.1 · last checked 20 Nov 2026

Europe's real AI bottleneck: the grid queue.

How much new demand is asking to plug into each country's grid, and what grid operators are doing about it. 14 countries, every figure with a source (11 straight from the grid operator, regulator or government). The published figures add up to 367 GW of data centres asking for, or holding, a grid connection, and Norway has paused new data centre connections.

Data centres in the queue, GW

Data centre share where the operator publishes it; * = only an all-sector figure exists. Stages differ (requests, queue, reserved, granted), so read the table before comparing. Colour = size against the country's average load: green under 2×, amber 2–5×, orange above 5×.

PolandPoland: 130 GW130 GWItalyItaly: 101 GW101 GWUnited KingdomUnited Kingdom: 73 GW73 GWDenmark*Denmark*: 60 GW60 GWNorwayNorway: 27 GW27 GWFranceFrance: 18 GW18 GWNetherlands*Netherlands*: 10 GW10 GWSpainSpain: 6 GW6 GWSwedenSweden: 6 GW6 GWFinlandFinland: 5 GW5 GWPortugal*Portugal*: 5 GW5 GW

Queue compared with the country's average load

The same GW divided by average electricity load (annual demand ÷ 8,760 h, Ember/OWID). Above 1× means the queue alone is bigger than the whole country uses on an average hour. Denmark leads at 12.9×.

Denmark*Denmark*: 12.9×12.9×PolandPoland: 6.5×6.5×ItalyItaly: 2.9×2.9×United KingdomUnited Kingdom: 2.0×2.0×NorwayNorway: 1.7×1.7×Netherlands*Netherlands*: 0.7×0.7×Portugal*Portugal*: 0.7×0.7×FinlandFinland: 0.5×0.5×SwedenSweden: 0.4×0.4×FranceFrance: 0.3×0.3×SpainSpain: 0.2×0.2×

Country by country

Policy:
CountryQueue× avg loadPolicyWhat it counts · what changedSource
Poland
PSE
130.0 GW
requests
6.5×Rules tightenedData centre connection requests, as reported from PSE (PSE does not publish a data centre split itself). PSE's draft network plan assumes only about 3 GW of data centre connection capacity by 2036. The Grid Act (April 2026) adds collateral and milestone deadlines, so inactive projects lose their rights.Press
Apr 2026
PSE network plan (WBJ)
United Kingdom
NESO / Ofgem (Great Britain)
125.0 GW
contracted queue · data centres 73 GW
2.0×Rules tightenedContracted demand in the GB connection queue; about 73 GW (315 projects) are data centres. Ofgem proposed a data centre commitment fee of £237,500 to £712,500 per MW (July 2026) to clear non-viable projects. GB peak demand was 45 GW in February 2026.Official
Mar 2026
Italy
Terna
101.4 GW
requests
2.9×Rules tightenedData centre connection requests on Terna's Econnextion portal (553 requests), as reported in the press. Terna's own last published figure: over 50 GW from 300+ projects (June 2025). Terna screens requests through its 'efficient territorial planning' model. Requests grew from about 30 GW at end 2024. Most are in Lombardy.Press
Aug 2026
Terna, June 2025
Denmark
Energinet
60.0 GW
waiting
12.9×Rules tightenedNew consumption projects waiting to connect across the transmission and distribution grids, driven by data centres, power-to-X and batteries. Energinet paused new connection agreements from early March to 3 June 2026 and replaced first come, first served with batch assessment ('first ready, first served'). No new agreements before autumn 2026; very large connections may take 5 to 10 years. Peak demand is about 7 GW.Official
Mar 2026
Energinet, new model (May 2026)
Norway
Statnett
27.1 GW
queue + requests
1.7×PausedData centres: 9.1 GW in the capacity queue plus 18 GW of further requests (4.2 GW reserved, 0.8 GW connected). New data centre capacity reservations paused from 9 November 2026, expected to lift by 1 August 2027 at the latest, while Statnett sets technical requirements for approval by the regulator RME. Peak consumption is just over 25 GW.Official
Nov 2026
France
RTE
18.0 GW
reserved
0.3×Fast trackGrid capacity reserved by RTE for about 80 data centre projects (up from about 5 GW for 40 projects at end 2024). RTE is fast-tracking five very large data centre projects (700 to 2,000 MW) and will switch to 'first ready, first served' by the end of 2026. Data centres took 3.8 GW of new grid contracts in the first half of 2026.Official
May 2026
RTE, H1 2026 review
Netherlands
Regional grid operators (Netbeheer Nederland)
10.0 GW
waiting list
0.7×Rules tightenedCapacity requested by 15,498 applicants on regional waiting lists for consumption (all sectors), plus 205 requests at TenneT. Grid congestion covers most of the country. New allocation rules apply from 1 July 2026, and operators are tendering flexible capacity to connect part of the queue sooner.Official
Jun 2026
Spain
Red Eléctrica (REE)
6.3 GW
granted
0.2×AuctionsTransmission access already granted to data centres (34% of all granted demand access); none in service yet. Spain allocates demand access at congested nodes by auction: the first round (February 2026) awarded 928 MW at eight nodes. REE says firm demand capacity is available at more than 35% of nodes.Official
Sep 2026
MITECO auction
Sweden
Svenska kraftnät
6.0 GW
requests
0.4×OpenNew data centre applications in bidding zone SE3 (Stockholm and Gothenburg) since Svenska kraftnät's 2024 analysis. Svenska kraftnät uses a stepwise connection process and plans a pilot on capacity zones. No national pause. In 2025, over 14 GW left its queue after missing contract deadlines.Official
Feb 2026
Svk queue by zone
Finland
Fingrid
5.0 GW
signed agreements
0.5×Rules tightenedPlanned final capacity of data centre projects with signed connection agreements (developer figures). Fingrid says a signed agreement does not guarantee full build-out; if all were built, Finnish consumption would rise about 40%. Its new grid code for demand above 30 MW (target March 2027) requires flexibility, and requests are processed by project maturity.Official
Aug 2026
Priority rules (Borenius)
Portugal
REN
4.6 GW
expressions of interest
0.7×AuctionsExpressions of interest in the nationwide large-demand zone. Stricter access conditions cut 13 requests worth 46 GW to about 4 GW. Since February 2026 all of mainland Portugal is a large-demand zone with higher deposits. REN says about €400m of reinforcement is needed; in October 2026 the government sent the capacity to auction instead of approving REN's dedicated plan.Press
May 2026
DGEG large-demand zone
Auction decision (ECIJA)
Germany
50Hertz, Amprion, TenneT, TransnetBW
–
not published
–Rules tightenedNo data centre figure. The four transmission operators held 717 applications worth about 270 GW, of which 211 GW were batteries; the other ~59 GW include data centres and electrolysers. Since 1 April 2026 the transmission operators assess large consumers, including data centres, in batches by project maturity instead of first come, first served. Regionally, about 22 GW of data centre enquiries reached Brandenburg since 2022.Official
Sep 2025
Regional figures (AlgorithmWatch)
Ireland
EirGrid / ESB Networks
–
not published
–ConditionalNo queue figure published. Data centres used 9.4 TWh in 2025, heading for 31% of national demand by 2034. The de facto Dublin moratorium was replaced by the CRU's connection policy: new data centres must bring matching on-site or local generation or storage, and EirGrid maps constrained areas.Official
May 2026
Belgium
Elia
–
not published
–Rules tightenedNo GW figure published. Data centre requests are reported up about nine-fold since 2022. The regulator CREG's revised code of conduct allows anti-dormant-capacity clauses in connection contracts, and Elia consulted on them in March 2026. Elia has also floated a separate, capped category for data centres (press, October 2025).Official
Mar 2026
Cap proposal (Brussels Times)

Method: figures as published, not normalised. "Requests" are applications; "queue" and "reserved" have passed a first check; "granted" holds access rights. Most requests will never be built: queues are inflated by speculative and duplicate applications, which is why operators are adding fees, maturity tests and auctions. "Official" = grid operator, regulator or government; "Press" = trade press, law firm or analyst, used only where the operator has not published the latest figure itself (its own figure is linked below when one exists). Great Britain's queue is compared with UK-wide demand. Have a newer official figure? It needs a public source to be listed.

Corrections & change log

Every change to a published figure is logged here with the reason. Spotted an error or have a newer official figure? Report it on GitHub (public, no account needed to read). How we pick sources: sourcing & corrections policy.

2026-11-20 · v1.1 · Checked every row against official sources
  • Denmark: status changed from 'Paused' to 'Rules tightened'. Energinet's pause ran from early March to 3 June 2026 and was replaced by batch assessment. The data centre figure (14 GW, from press) was removed because Energinet does not publish it; the chart now uses the official all-sector 60 GW, marked *.
  • Finland: 24 GW of requests (press) replaced by Fingrid's own figure, about 5 GW of data centre projects with signed connection agreements (August 2026).
  • Portugal: 41 GW removed; the source we cited did not contain it. Replaced by 4.6 GW of expressions of interest (May 2026), after stricter rules cut 46 GW of requests to about 4 GW.
  • Sweden: 6.7 GW (press) replaced by Svenska kraftnät's figure of about 6 GW of new data centre applications in SE3 (February 2026).
  • Belgium: status changed from 'Cap proposed' to 'Rules tightened'. The data centre cap was only reported in the press; the official measure is a crackdown on unused reserved capacity.
  • Norway, France, Spain, Netherlands, Germany: same figures, now linked to the grid operator's or regulator's own publication.
  • Italy and Poland: figures unchanged and still press-sourced, now labelled as such, with Terna's own older figure linked for Italy.
  • Headline reworded from 'GW of data centre requests' to 'GW of data centres asking for, or holding, a grid connection', because some figures are reservations or signed agreements.
2026-11-20 · v1.0 · Grid access tracker launched
  • 14 countries, figures mostly from trade press and law firms citing grid operators.